Da Nang Power Company (Da Nang PC) has carried out the acceptance test and put into operation the 110kV EMC transmission transformer at the location of T2 – 110kV Hoa Khanh 2 station. The successful energization of the T2 EMC transformer plays an important role in leveling the load for 110kV substations supplying power to the city center.

 

Hoa Khanh 2 110kV transformer station is located in Hoa Khanh Industrial Park, Hoa Khanh Bac ward, Lien Chieu district, Da Nang city. The station is invested and built for the purpose of supplying electricity to enterprises in Hoa Khanh Industrial Park, Expanded Hoa Khanh Industrial Park, Thanh Vinh Industrial Cluster and surrounding areas in Lien Chieu District, Hi-Tech Park; Quang Nam – Thuy Tu urban areas…

The investment in upgrading the 110kV Hoa Khanh 2 substation aims to improve the power supply capacity for Hoa Khanh Industrial Park and surrounding areas. At the same time, implementing social security policies, urban embellishment, attracting investment, ensuring timely for key projects, industrial zones, residential areas, resettlement areas according to the city’s planning guidelines Da Nang City.

Share: